Huyton Countdown - 28 Days

With 28 days to go until the new layout is operational, things are moving on as scheduled.  Today, the public subway was closed, and it is expected to be closed for a week.  The station subway re-opened, but only between platforms 1 and 2, the original section to platform 4 remains closed at the moment.  (None of the lifts are ready yet.)

There is a new temporary ramp, opened for the first time today, from Blacklow Brow leading to the ticket office and to the re-built stairs down to the subway.

The old ramp leading to platform 2 is closed and can now be demolished, along with the temporary footpath which is currently obstructing the new trackbed and the construction of part of platform 3.

So, a pedestrian wishing to walk from the south side to the north side starts with the new ramp, then down the stairs, through the subway, up to platform 2, along the platform towards Liverpool, across the "bridge" to platform 4, and then back along the full length of platform 4 to the new northern access.  I would advise any locals to go round via Archway Road - As indeed I will be doing this evening on my way to the pub.

Elsewhere in the area, there are plenty of new signals, mostly folded down but with one or two standing up.  Miscellaneous switch and crossing panels are stacked on the third track, near Huyton and at Roby Junction.  Mast bases are getting closer and closer, but so far they are avoiding Huyton Junction and Roby Junction.

5 comments:

  1. I received my briefing booklets at a special brief last week with an instructor.
    Alot of work has been invested in this project by all concerned.

    ReplyDelete
  2. There's also no mast bases (or sign of them) on Rainhill or Earlestown platforms?

    ReplyDelete
    Replies
    1. Yes, there's still lots more to do at various places. In general they seem to do the "easy" bits first and leave the complicated ones - station platforms, the canyon at Thatto Heath, etc etc - until last. I reckon provided Huyton goes OK next month things should be fine for electrification by December. All we need then is some trains...

      Delete
  3. I think the rocket is gonna return to service on that section of the line. :-D

    ReplyDelete
    Replies
    1. Now that would definitely be worth buying a savaway!

      Delete