Today Rail Minister Theresa Villiers announced details of the new trains
to be built by Siemens for the Thameslink line in London. The first of
these is scheduled to arrive in 2015. Some of the displaced Class 319
trains are to move to the Northwest.
So, the lines from Liverpool to Manchester and Wigan are scheduled to be
electrified by 2014, but the electric trains won't arrive until a year
later?
Thursday, 16 June 2011
Monday, 23 May 2011
New Liverpool South Parkway to Blackpool Service
From May 23 the existing Liverpool - Blackpool North service was
extended in off-peak daytime hours to and from Liverpool South Parkway.
This does not require any additional stock, as the trains previously
stood for 55 minutes at Lime Street.
Monday, 4 April 2011
Website Launched
The website www.nw-sparks.co.uk has been launched today. The site will
monitor and record progress on the project to electrify railways in
Northwest England.
Friday, 4 March 2011
Work Under Way
Network Rail has announced the beginning of actual work on the ground:
Work has commenced on the demolition and rebuilding of one pedestrian
bridge and two road bridges over the railway between Eccles and
Patricroft. This section of the line is scheduled to be electrified in
2013.
Thursday, 25 November 2010
Government Announces Go Ahead
Transport Secretary Philip Hammond has announced spending approval for a number of railway modernisation projects.
These include electrification in North West England, at a cost of "up to £300 million".
Work will commence in 2011 and should be completed in 2016.
These include electrification in North West England, at a cost of "up to £300 million".
Work will commence in 2011 and should be completed in 2016.