Sunday, 13 July 2014

Blockade Last Day

I passed by Huyton station a couple of times on Saturday and the big change is the total lack of ballast trains, big cranes, etc.  In other words, the major trackwork is probably complete.

There was plenty of other stuff going on, platforms were being surfaced, poster boards erected and so on.  S&T engineers were fiddling with wires.

So, it's all looking good.  Of course, there's lots of finishing work to be done, and then the small matter of electrification to deal with.

After posting the above I took a Sunday lunchtime stroll .  Huyton has gained an "OFF" indicator half way along platform 2, and departure displays on platforms 2 and 3, both lit. Another feature I've not reported before is a red signal at the west end of platform 3.  Presumably trains will be able to reverse in 3 as well as 2.

A lot of rail joints remain to be welded, but these can wait for night-time possessions next week.

At Roby, the edge of platform 3 is complete, with some final grouting under way.










I have been checking my notes for the previous re-modelling of Huyton Junction which was in 2007 when it was changed from a traditional double junction to the simplified double junction we had until last week.  This was completed in a four day Easter blockade and my logs show the trains running normally on the Tuesday morning.

Friday, 11 July 2014

Blockade Day 7

I visited Huyton station once again today:

Line 1 (Down Chat Moss Fast) is back in place, it has been relaid through the station, unlike line 2 (Down Chat Moss Slow) where the original track remains alongside the platform.
As you can see, line 1 still awaits ballasting, but is otherwise complete.

Here are the two signals just east of Huyton station.  The far one is for Up trains on line 3 (Up Chat Moss) with a position 1 junction indicator for trains towards Wigan.  The nearer one seems to be a new head on the original structure.  It is for trains reversing in platform 2 before heading towards Manchester.


NEWSFLASH FOR DATA GEEKS:  Since 11:25 this morning the Network Rail train describer data feed has been showing describer heartbeat and other signalling messages from describer "M1" which I believe is the new signalling here at Huyton.

UPDATE 19:30:  Line 1 has been ballasted during the afternoon.

Thursday, 10 July 2014

Blockade Day 6

Just a brief update.

At lunchtime today 70002 was on a ballast train on the newly re-laid line 2 (Down Chat Moss Slow), the ballast was being used to form the replacement trackbed for line 1 (Down Chat Moss Fast).


Wednesday, 9 July 2014

Blockade Day 5

We've reached the half-way point, and lunchtime on Wednesday found the track replaced on line 2 (Soon to be the Down Chat Moss Slow) but not yet ballasted.  Two rail-mounted cranes were operating on the new line 3 (Up Chat Moss).

Confused?  I posted a diagram in the blog last year.


Tuesday, 8 July 2014

Blockade Day 4

The Orange Army were hard at work when I visited Huyton this afternoon.

New signals have been erected.
A new shelter has appeared on platforms 2 and 3, matching the one which appeared on platform 4 last week.
Tracks 1 and 2 have been removed completely at the point where they pass over the subway.

It really is difficult to get a good view of what's going on without trespassing.  This is the best I can do, looking west from the east end of the station.

At the far end of the station you can just about see a giant signal gantry.

Returning to Huyton at about 19:30 I discovered a works train on the new third line with a class 60 on the front.
Later, on my way home from the pub at about half past ten, 70003 was doing the honours on a train carrying
new ballast which was being dumped on to the path of tracks 1 and 2.






 


Regular contributor David Hull was also out today, and he provided this shot of the new signal gantry at Roby.


David also provided this daylight shot of the missing lines 1 and 2.