Monday, 2 November 2015

Progress

Test Trains

A number of Pendolino test trains are scheduled to run on Tuesday night / Wednesday morning.  I believe these are to test the newly completed autotransformer feed system.

5T80 23:24 Edge Hill Depot to Manchester Piccadilly via Lime Street and Chat Moss
5T81 00:41 Manchester P to Manchester P via Chat Moss, Lime Street and Chat Moss
5T82 02:18 Manchester P to Wigan NW via Chat Moss, Lime Street and Golborne
5T83 03:51 Wigan NW to Wigan NW via Golborne, Lime Street and Golborne
5T84 05:19 Wigan NW to Edge Hill Depot via Golborne and Lime Street

I am told that the Wigan runs may be altered to operate via St Helens Central.

If successful, I think this could mark the final completion of Phase 2 at last.  Apart from the footbridge fiasco at Rainhill, which seems to have been forgotten.

Huyton Fourth Track

It may be nothing to do with the railway, but I noticed a gang of people in orange dress in the car park of Huyton Telephone Exchange this morning.  They had a theodolite positioned on the future location of the fourth track.  Could this indicate that work is to begin soon?

Completion of the fourth track will require a slice of land to be removed from the telephone exchange car park (But will just squeeze past the actual building, I think.) and also a longer slice off the side of Huyton bus station.  Permission for these works has been granted in a Transport and Works Act Order.

Once the land has been cleared it will "simply" be a matter of  stringing up some overhead, installing points at Roby Junction, re-modelling Huyton Junction, and altering the signalling.

Unusual Track

The line to Manchester was closed for engineering works yesterday, resulting in the Liverpool to Manchester Airport service being diverted to Wigan North Western, thus giving the west curve at Parkside a rare regular service.

Normally, this route has just one passenger train one way on weekdays, the 06:44 Wigan North Western to Liverpool Lime Street.

At Wigan, the service was reversing in platform 1, not normally used by class 319 units.


I'm not sure why the trains didn't reverse at Earlestown as they did on Saturday.
(Correction:  The service terminated at Earlestown on Saturday, but the trains ran on to Parkside Junction to reverse.)

Update:   For anyone who wants to try out this unusual route, similar operations are scheduled for the first three Sundays in 2016.

Friday, 16 October 2015

Timetable Tweak

I noticed something rather odd in the daily updates to the timetable database this morning:  A number of schedules for the Liverpool / Preston services in the next timetable period (13 December 2015 to 14 May 2016) had been deleted and re-inserted.

Naturally I investigated, looking for the difference between the old and new versions, and I was surprised to see that the trains have been promoted from class 2 to class 1.  So, for example, 2N76 09:28 Liverpool Lime Street High Level to Preston has been deleted, and replaced by 1N82 09:28 Liverpool Lime Street High Level to Preston.

The timings remain exactly the same, and the rolling stock is still indicated as "DMU Class 150, 153, 155 or 156".

I wonder what the significance of this change is, if any?  Perhaps the signalmen will give these priority over the stopping services.

Tuesday, 13 October 2015

Carillion Is New Contractor

Carillion has won the Network Rail contract for the Northwest Electrification project formerly held by Balfour-Beatty.

Hopefully we will soon see work on the Manchester to Preston phase moving ahead once more.

Friday, 9 October 2015

News Roundup

New Timetable

The new timetable, from Sunday 04 October, has introduced some more electric workings.  On Mondays to Saturdays almost all Liverpool/Blackpool services are cut back to Preston and operated by 319s, requiring a further three units in operation.  The extension of most of these services to Liverpool South Parkway still applies, so we have gained regular 319 operation in passenger service there as well.

Here we see 319369 basking in the autumn sunshine at South Parkway, having arrived from Preston via Lime Street and waiting to form the 11:03 return service.

On the other hand, the Liverpool/Warrington Bank Quay services remain mainly diesel operated, although I think the 17.50 off Lime Street and 18.52 return might now be electric.

Farnworth Tunnel

Fillie continues her slow progress under Farnworth.  The timetable database currently shows normal trains along this line from Monday 14 December, but I'm not sure how much weight we can give to that information.

Contractors

Unless I've missed it, we still haven't had a formal announcement of which company or companies are to take over from Balfour Beatty and undertake the remaining parts of the project.